Decision Science | Chapter 3 | Part 4 | MBA MCQs | DS
Decision Science MCQs
Decision Science MCQs
In an assignment problem involving 5 workers and 5 jobs, total number of assignments possible are _______.
5
10
15
20
In marking assignments, which of the following should be preferred?
Only row having single zero
Only row/column having single zero
Column having more than one zero
Only column having single zero
The average arrival rate in a single server queuing system is 10 customers per hour and average service rate is 15 customers per hour. The average time that a customer must wait before it is taken up for service shall be _______minutes
6
8
10
12
Customers arrive at a box office window, being manned ny single individual, according to Poisson input process with mean rate of 20 per hour, while the mean service time is 2 minutes. Which of the following is not true for this system?
E(n) = 2 customers
E(m) = 4/3 customers
E(m) = 4/3 customers
E(w) = 16 minutes
A petrol pump has two pumps; Vehicles arrive at the petrol pump according to poison input process at average of 12 per hour. The service time follows exponential distribution with a mean of 4 minutes. The pumps are expected to be idle for _____.
33%
53%
65%
43%
A game is said to be fair if_________.
lower and upper values are zero
only lower value to be zero
only upper value to be zero
lower and upper values are not equal to zero
In Program Evaluation Review Technique the maximum time that is required to perform the activity under extremely bad conditions is known as_____.
normal time
optimistic time
most likely time
pessimistic time
_____is a mathematical technique used to solve the problem of allocating limited resource among the competing activities
Linear Programming problem
Assignment Problem
Replacement Problem
Non linear Programming Problem
A game is said to be strictly determinable if________.
maximin value equal to minimax value
maximin value is less than or equal to minimax value
maximin value is greater than or equal to minimax value
maximin value is not equal to minimax value
A mixed strategy game can be solved by ____.
Simplex method
Degeneracy
Graphical method
Hungarian method
When the sum of gains of one player is equal to the sum of losses to another player in a game, this situation is known as_____.
two-person game
two-person zero-sum game
zero-sum game
non-zero-sum game
Graphical method of linear programming is useful when the number of decision variable are _______
2
3
4
5
The activity cost corresponding to the crash time is called the _____.
critical time
normal time
cost slope
crash cost
The irreducible minimum duration of the project is called______.
critical time
normal time
cost slope
crash duration
In the network, one activity may connect any _______nodes
1
2
3
4
The application of OR techniques involves ………… approach
Individual
Team
Critical
None of the above
The mathematical technique for finding the best use of limited resources of a company in a maximum manner is known as:
Value analysis
Investment analysis
Linear programming
Queuing theory
Management science and operations research both involve
Qualitative managerial skills
Quantitative approaches to decision making
Operational management skills
Scientific research as opposed to applications
The quantitative analysis approach requires
the manager's prior experience with a similar problem
a relatively uncomplicated problem
mathematical expressions for the relationships
each of the above is true
Which of the following is not the characteristics of the LPP
Resources must be limited
Only one objective function
The problem must be of minimization type
Parameters value remains constant during planning period