Decision Science | Chapter 3 | Part 4 | MBA MCQs | DS
Decision Science MCQs
- In an assignment problem involving 5 workers and 5 jobs, total number of assignments possible are
_______.- 5
- 10
- 15
- 20
- In marking assignments, which of the following should be preferred?
- Only row having single zero
- Only row/column having single zero
- Column having more than one zero
- Only column having single zero
- The average arrival rate in a single server queuing system is 10 customers per hour and average service
rate is 15 customers per hour. The average time that a customer must wait before it is taken up for service
shall be _______minutes- 6
- 8
- 10
- 12
- Customers arrive at a box office window, being manned ny single individual, according to Poisson input process with mean rate of 20 per hour, while the mean service time is 2 minutes. Which of the following is not true for this system?
- E(n) = 2 customers
- E(m) = 4/3 customers
- E(m) = 4/3 customers
- E(w) = 16 minutes
- A petrol pump has two pumps; Vehicles arrive at the petrol pump according to poison input process at
average of 12 per hour. The service time follows exponential distribution with a mean of 4 minutes. The
pumps are expected to be idle for _____.- 33%
- 53%
- 65%
- 43%
- A game is said to be fair if_________.
- lower and upper values are zero
- only lower value to be zero
- only upper value to be zero
- lower and upper values are not equal to zero
- In Program Evaluation Review Technique the maximum time that is required to perform the activity under extremely bad conditions is known as_____.
- normal time
- optimistic time
- most likely time
- pessimistic time
- _____is a mathematical technique used to solve the problem of allocating limited resource among the
competing activities- Linear Programming problem
- Assignment Problem
- Replacement Problem
- Non linear Programming Problem
- A game is said to be strictly determinable if________.
- maximin value equal to minimax value
- maximin value is less than or equal to minimax value
- maximin value is greater than or equal to minimax value
- maximin value is not equal to minimax value
- A mixed strategy game can be solved by ____.
- Simplex method
- Degeneracy
- Graphical method
- Hungarian method
- When the sum of gains of one player is equal to the sum of losses to another player in a game, this
situation is known as_____.- two-person game
- two-person zero-sum game
- zero-sum game
- non-zero-sum game
- Graphical method of linear programming is useful when the number of decision variable are _______
- 2
- 3
- 4
- 5
- The activity cost corresponding to the crash time is called the _____.
- critical time
- normal time
- cost slope
- crash cost
- The irreducible minimum duration of the project is called______.
- critical time
- normal time
- cost slope
- crash duration
- In the network, one activity may connect any _______nodes
- 1
- 2
- 3
- 4
- The application of OR techniques involves ………… approach
- Individual
- Team
- Critical
- None of the above
- The mathematical technique for finding the best use of limited resources of a company in a maximum manner is known as:
- Value analysis
- Investment analysis
- Linear programming
- Queuing theory
- Management science and operations research both involve
- Qualitative managerial skills
- Quantitative approaches to decision making
- Operational management skills
- Scientific research as opposed to applications
- The quantitative analysis approach requires
- the manager's prior experience with a similar problem
- a relatively uncomplicated problem
- mathematical expressions for the relationships
- each of the above is true
- Which of the following is not the characteristics of the LPP
- Resources must be limited
- Only one objective function
- The problem must be of minimization type
- Parameters value remains constant during planning period