Decision Science | Chapter 4 | Part 1 | MBA MCQs | DS
Decision Science MCQs
- To use the Hungarian method, a profit-maximization assignment problem requires
- matrix expansion.
- converting all profits to opportunity losses.
- dummy agent or task.
- finding the maximum number of lines to cover all the zeros in the reduced matrix.
- The critical path
- is any path that goes from the starting node to the completion node.
- is a combination of all paths.
- is the longest path.
- is the shortest path.
- When activity times are uncertain,
- assume they are normally distributed..
- Calculate the expected time, using (a + m + b)/3
- use the most likely time.
- calculate the expected time, using (a + 4m + b)/6.
- The critical path is the __________ path through the network.
- longest
- shortest
- straightest
- none of the above
- In a CPM/PERT network the critical path is the
- lowest path through the network
- longest path through the network
- shortest path through the network
- highest path through the network
- The transportation model relies on certain assumptions. They include all of the following except
- the items must be homogeneous
- there is only one route being used between each origin and destination
- the shipping cost per unit is the same
- the items must be large scale
- Which of the following are supply points that a transportation model can analyze?
- Factories
- warehouses
- departments
- all of the above
- event represents beginning of more than one activities
- burst
- none of them
- merge
- dummy
- Merge event represents of two or more events
- beginning
- completion
- none of them
- splitting
- Activity which is completed before starting new activity is called .
- dummy
- predecessor
- none of them
- successor
- The Objective of network analysis to
- Minimize total project duration.
- Minimize total project cost
- Minimize production delays, interruption and conflicts
- All of the above
- Network models have advantage in terms of project
- Planning
- All of the above
- Scheduling
- Controlling
- The slack for an activity is equal to
- LF-LS
- LS-ES
- EF-ES
- None of the above
- The Another term commonly used for activity slack time is
- Total float
- Free float
- All of the above
- independent float
- If an activity has zero slack, it implies that
- It lies on the critical path
- It is a dummy activity
- The project progressing well
- None of the above
- A dummy activity is used in the network diagram when
- Two parallel activities have the same tail and head events
- The chain of activities may have a common event yet be independent by themselves
- None of the above
- Both A and B
- While drawing the network diagram , for each activity project, we should look
- What activities precede this activity?
- What activities follow this activity?
- What activities can take place concurrently with this activity?
- All of the above
- The critical path satisfy the condition that
- Ei = Li & E j = Lj
- Lj-Ei=Li-Ej=c(constant)
- All of the above
- Lj-Ei=Li-Lj
- If there are in jobs to be performed, one at a time, on each of m machines, the possible sequences would be
- (n!)^m
- (n)^m
- (m!)^n
- (m)^n
- Total elapsed time to process all jobs through two machine is given by
- n n
Σ M1j + Σ M2j
j=1 j=1 - n n
Σ M2j + Σ M1j
j=1 j=1 - n
Σ (M1j + I1j)
j=1 - None of the above
- n n
0 Comment:
Post a Comment